• blackbeans@lemmy.zip
    link
    fedilink
    English
    arrow-up
    14
    ·
    2 days ago

    From what I read, it does 800 MW max, which is still a lot.

    1.2 GWh is just the capacity. And response time can indeed be quite fast as the system is always on standby, but I would guess it would still take a few seconds to go from zero to full power

    • elmicha@feddit.org
      link
      fedilink
      English
      arrow-up
      13
      ·
      2 days ago

      But with 800 MW it takes an hour and a half to get to 1.2 GWh, and an hour is 3600 seconds or 3600000 ms. So “a few” is doing a lot of work in that quote.

      • blackbeans@lemmy.zip
        link
        fedilink
        English
        arrow-up
        4
        ·
        2 days ago

        The quote is obviously incorrect, perhaps the engineer meant to say “absorb 1.2 GWh and start providing power to the grid in a matter of milliseconds”, and it was lost in translation.